Procedures for
Minor
Modification
with Construction
Both Title V and SIP applications must be submitted to EPD. The Title V application must consist of at least the following completed sections:
A - Facility Information
B - Facility Emissions
C - Rule Applicability (for ENTIRE facility)
Any other sections that pertain to changes being made.
Notarized certification page signed by the "responsible official."
Construction may begin upon the
facility's receipt of the SIP Construction/proposed operating
permit. The final approval letter must be received by the
facility before commencing operation.
EPA has a 45-day review period,
but there is no public comment period. At the end of EPA's
review period, a letter will be sent to the facility advising
that the permit is final or a new permit will be issued.
The application must include a
description of the change, the emissions resulting from the
change, and any new applicable requirements.