Both Title V and SIP applications must be submitted to EPD. The Title V application must consist of at least the
following completed sections:
- A - Facility Information
- B - Facility Emissions
- C - Rule Applicability (for ENTIRE facility)
- Any other sections that pertain to changes being made.
- Notarized certification page signed by the "responsible official."
-
Construction and operation may begin upon the
facility's receipt of the SIP construction/proposed operating
permit.
-
EPA has a 45-day review period,
but there is no public comment period. At the end of EPA's
review period, a letter
will be sent to the facility advising
that the permit is final or a new permit will be issued.
- The application must include a
description of the change, the emissions resulting from the
change, and any new
applicable requirements.
- The applicant may submit a
"suggested permit."
|